IEC 62619 for Energy Storage Batteries: Key Certification Points and Timeline Budgeting

Editor:ESTL Category:Certification information Release time:2026-10-26 Click volume:6

IEC 62619 for Energy Storage Batteries: Key Certification Points and Timeline Budgeting

A standard-applicability briefing for storage battery manufacturers, system integrators and exporters: how the levels are divided, what changed in the 2022 edition, and how to plan the timeline and documentation.

THE SHORT ANSWER

Lithium-ion batteries for stationary storage, telecom backup, UPS and other industrial scenarios are usually assessed against IEC 62619, and the current edition is IEC 62619:2022 (second edition, published on 24 May 2022). Assessment is carried out separately at the cell, battery and battery system levels, and a cell report cannot substitute for battery-level requirements. The 2022 edition added the thermal propagation test, BMS functional safety, overcurrent protection and EMC requirements. With complete documentation, the period from project opening to report is about 6 to 10 weeks, and applying for a CB certificate at the same time adds another 2 to 3 weeks.

1. Why Energy Storage Batteries Map to IEC 62619, and Not to Other Standards

In storage battery exports and domestic project tenders, IEC 62619 is among the safety standards cited most frequently. Published by the International Electrotechnical Commission (IEC), it is titled Secondary cells and batteries containing alkaline or other non-acid electrolytes — Safety requirements for secondary lithium cells and batteries, for use in industrial applications. It covers lithium-ion cells, batteries and battery systems in industrial applications and sets out functional safety related requirements for battery management systems (BMS).

A one-line judgement

Look at how the product is used: fixed installations, backup power and industrial vehicles correspond to IEC 62619; products carried on the person correspond to IEC 62133-2; traction batteries for road vehicles correspond to the IEC 62660 series. Which standard a product falls under is determined by its end application and the purchaser's requirements.

Storage-related scenario Relevant standard Notes
Grid-side / C&I / residential storage, containerized storage IEC 62619 The primary standard for industrial lithium battery safety
UPS, telecom base station backup, data centre backup IEC 62619 Stationary backup scenarios usually rely on this standard
Portable power supplies, outdoor power stations IEC 62133-2 Portable electronic products and equipment; not an industrial scenario
Electric forklift and AGV batteries IEC 62619 Batteries for industrial mobile equipment are within scope
Traction batteries for road vehicles IEC 62660 series Where the two apply in parallel, the vehicle standard takes precedence
Whole-system level of storage systems IEC 63056 and others System-level requirements are often used together with IEC 62619

A boundary that is often overlooked

The standard applies to new cells and batteries and does not cover reuse, recycling or other second-life situations. For storage products assembled from retired traction batteries under a second-life scheme, the condition of the product and the assessment premises need to be confirmed separately, and the usual test plan cannot be applied directly.

2. Cells, Battery Packs, Systems: Three Levels Tested Separately

IEC 62619 assesses products by level, and the test content at the three levels differs; none can substitute for another.

Cell level: the safety of the cell itself

Category Typical items What is assessed
Electrical safety Overcharge, external short circuit, forced discharge, overdischarge No fire or explosion under abnormal electrical conditions
Mechanical safety Crush, impact, drop, vibration, shock No leakage, fire or explosion after mechanical stress
Environmental safety Temperature cycling, high temperature use, low pressure, damp heat Thermal stability and seal integrity
Thermal safety Thermal abuse Whether failure behaviour is controllable above the maximum operating temperature

Battery and system level: protection functions and system behaviour

Item Assessment points
Overcharge / overdischarge protection Verify that protection operates at battery level; record operating time and state
External short circuit / overcurrent protection Short-circuit current interruption capability and temperature rise; whether protection triggers correctly under abnormal current (new in 2022)
Thermal propagation After triggering thermal runaway in a single cell, whether the failure is contained within the system boundary (strengthened in 2022)
BMS functional safety Monitoring logic, fault detection and cut-off response, safe state after communication failure
EMC BMS protection functions are not falsely triggered or lost under external electromagnetic interference (new in 2022)
Structure and marking Terminal connections, insulation and wiring, protection of hazardous live parts, marking and installation information

A cell report cannot replace battery pack testing

Overcharge protection, overdischarge protection, external short circuit, overcurrent protection and BMS-related requirements at battery level must be performed again at battery or system level. When purchasers review reports they usually check which level the report corresponds to, and a report at the wrong level cannot be used for tenders or delivery.

3. What the New 2022 Requirements Mean for Storage Projects

IEC 62619:2022 moves the focus of assessment from "cells and batteries" towards "battery systems", with changes concentrated in system-level safety design. For storage projects, the direct impact falls on structural design and BMS documentation.

New direction Content Impact on storage projects
Thermal propagation The propagation test is formally incorporated, with an added laser-triggered method Module and rack level structures need design addressing the propagation path; sample preparation increases
BMS functional safety New safety analysis requirement, which may follow frameworks such as IEC 61508 and ISO 13849 BMS architecture, monitoring logic and fault response descriptions must be submitted
Overcurrent protection Verify that protection operates correctly under abnormal charge and discharge current Protection thresholds and response times must match the design documentation
EMC Confirm that BMS protection functions are not affected by external electromagnetic interference Immunity design enters the assessment and can be tested on the end product
System lock and safe state After a fault, enter a stop state that the user cannot reset Software logic must be designed so it does not self-recover after a fault
Structure and installation Moving parts, hazardous live parts, terminal connections, installation and storage information Structural design and installation manuals need corresponding additions

On reports to the previous edition: the accepting party's requirements govern

A change of standard edition does not automatically mean that an existing test report loses its meaning. Whether a report is accepted depends on the specific requirements of the purchaser, platform, regulator or certification body in the target market. We suggest confirming with the accepting party which edition it accepts first, and then assessing whether gap testing is needed, so as to avoid unnecessary repeat testing.

4. Certification Path and Timeline Budget

Standard determination and level confirmation

Establish whether the product is a cell, a battery or a battery system, and clarify the end application and the acceptance requirements of the target market.

Gap analysis

Where reports to other standards or to the earlier edition exist, compare test scopes item by item to establish the items to be supplemented, avoiding a full round of retesting.

Documentation and sample preparation

Datasheets, BMS design and fault logic descriptions, structural drawings, key component lists and marking documents; prepare samples according to the plan.

Test execution

Cell level first, then battery and system level; thermal propagation and BMS functional safety have the longest lead times and should be scheduled early.

Report issue

After testing passes, the report is compiled and reviewed; where nonconformities arise, the product is adjusted in line with the laboratory's comments and retested.

CB certificate application and conversion

Where multi-country access is needed, apply to an NCB for a CB certificate based on the report, then supplement national differences as required by the target country to convert into local approvals such as CE and KC.

Typical time to report

6–10 weeks

Overall range from project opening to report, assuming complete documentation and no nonconformities

CB certification body review

2–3 weeks

Additional review time to apply for a CB certificate after the report is complete, depending on NCB scheduling

Nonconformity retesting

2–4 weeks

Additional time for a single retest; it may be longer if new samples are required

Large-capacity storage battery system samples are bulky, charge and discharge cycling takes a long time, and multiple batches cannot easily run in parallel, which are the main factors that extend the timeline. Where a tender or grid-connection date is fixed, we suggest moving the testing forward to the design freeze stage.

Document checklist

Category Content
Product technical documentation Cell and battery datasheets, rated parameters, series and parallel configuration and assembly method
BMS documentation Architecture description, monitoring and protection logic, fault response strategy, communication protocol, software version description
Structural and electrical documentation Structural drawings, terminal and wiring descriptions, insulation design, key component list and certificates
Marking and instructions Nameplate and label artwork, installation manual, safety warning content
Samples Cells and battery/system samples identical to production status, in quantities confirmed per project

5. Four Misjudgements Common in Storage Projects

Misjudgement 1: Submitting storage batteries as portable products

Using IEC 62133-2 for grid-connected storage or telecom backup batteries results in test items and acceptance logic that do not match, and the report cannot be used in the target market. Confirm the end application before submitting.

Misjudgement 2: Assuming a cell report covers the system

Protection functions, BMS, EMC and thermal propagation at battery level must be assessed independently at battery or system level, and a cell-level report cannot replace them.

Misjudgement 3: Using an IEC 62619 report directly for the North American market

The North American market relies primarily on UL 1973, UL 9540 and similar standards, which differ in areas such as BMS redundancy, single-fault tolerance and contactor weld detection. A CB report can serve as a technical basis, but the differing items usually need supplementary testing.

Misjudgement 4: Overlooking BMS software documentation

The 2022 edition brings BMS functional safety into scope. Missing architecture descriptions, fault response logic or communication failure handling directly slow progress, so they should be prepared alongside the hardware documentation.

Frequently Asked Questions

Should a residential energy storage battery be tested to IEC 62619 or IEC 62133-2?
The choice is determined by the end application and the purchaser's requirements. Stationary scenarios such as residential storage, commercial and industrial storage and telecom backup are usually assessed against IEC 62619, while portable products such as portable power supplies and outdoor power stations usually correspond to IEC 62133-2. Before opening a project, we suggest confirming with the purchaser or integrator which standard it accepts, and then arranging the testing.
For energy storage batteries exported to Europe, is an IEC 62619 report sufficient?
IEC 62619 covers the safety testing level for industrial lithium batteries; exports to Europe usually also need to be combined with other directives and harmonized standards under the CE framework. A report under the CB Scheme can serve as a technical basis and reduce duplicate testing, but the final requirements are those of the purchaser, the notified body or the regulator. We suggest confirming the scope of acceptance before opening a project.
A tender requires an IEC 62619 report and the timeline is tight. What can be done?
We suggest moving the testing forward to the design freeze stage and completing a gap analysis before the project opens. Where reports to other standards already exist, compare the test scopes item by item to establish whether only gap items need to be performed; thermal propagation and BMS functional safety have the longest lead times and should be scheduled early. Before the project opens, confirm the test items, sample quantities and milestones in a written plan.
How detailed should the BMS documentation be?
The 2022 edition brings BMS functional safety into the assessment. The documentation usually needs to cover: the BMS architecture description, voltage, current and temperature monitoring and protection logic, fault detection and response strategies, communication protocols and the safe state after communication failure, and the software version description. Missing documents directly slow progress, so they should be prepared alongside the hardware documentation.
We already hold a 2017 edition report. Can it still be used now that the 2022 edition has been published?
Whether a report is accepted depends on the specific requirements of the purchaser, platform, regulator or certification body in the target market; the change of edition does not by itself determine whether a report remains usable. When responding to a customer's compliance enquiry or planning a new project, we suggest confirming with the accepting party which standard edition it accepts first, and then assessing whether gap testing is needed.

IEC 62619 Test Plans and Schedule Assessment for Storage Batteries

Whether at cell, battery or system level, we can provide technical support for standard determination, gap analysis, test execution and CB conversion. Tell us your product type, target market and key dates, and we will set out the corresponding plan and schedule.

Guangdong ESTL Technology Co., Ltd. · Website: www.gdestl.com

This page is compiled and published by Guangdong ESTL Technology Co., Ltd. and is provided for industry reference only; it is not legally binding, and the content was prepared with AI assistance. Standard numbers, editions, implementation dates and technical requirements are subject to the official texts published by the IEC and the relevant target markets; specific certification conclusions are subject to assessment by the certification body.

Label: Energy Storage Batteries Certification CB certification IEC 62619
logo
Service HotlineWhatsApp:+86 13925582920
Address: 2st floor, B Area, Jinbaisheng Industrial Park, Headquarters 2 Road, Songshan Lake Hi-tech Industrial Development Zone, Dongguan City, Guangdong Pr., China. Telephone: Email:net03@gtggroup.com Fax: +86-0769-85075898 Mailbox: net03@gtggroup.com
Wechat Public Number

Focus on Wechat
Public Number

Hotline

WhatsApp:+86 13925582920
Email:net03@gtggroup.com
Tel:+86 13925598091 7*24-hour service hotline

QQ

Wechat

二维码Focus on Wechat
TOP